American Terawatt · underground HVDC

Corridor Delivery Plan

Buried high-voltage line, route to firm power at your site.

What It Is

A 200-mile strip of land with a DC cable buried under it, carrying 2 GW of firm power from generation to your site.

How It Is Built

Five steps, each ending in a decision. Land, permits and equipment are secured one step at a time, so a route that hits a problem stops early rather than half built.

Why Several Routes

Not every route clears every step. Several run in parallel so the power still arrives on schedule.

The Plan

The Five Steps

Nothing in a later step is committed until the one before it is done.
StepWhat must be trueChance it clears

Schedule, One Corridor

Each bar is a workstream. Dotted lines are the five decisions.
Step 1, generation Step 2, permits and land Step 3, closing Step 4, cabling Step 5, energization

Routes Surviving Each Step

Chance at Least One Delivers
·
Across every route developed.
Expected Capacity Energized
·
Routes clearing all five steps, times capacity each.
Time to First Power
·
Months from start.

Value to You

Your value per GW, set in the controls below.
One Corridor, Energized
·
Capacity times value per GW.
Value in Today's Money
·
Discounted back from month ·.
Expected Across the Programme
·
Weighted by the capacity expected to energize.

Assumptions

Every figure above is driven by these. The step odds are our judgement today.
10
2 GW
60%
200 mi
40%
36 mo
80%
95%
97%
$2.5B
15%
Timing of each step
3 mo
9 mo
9 mo
12 mo
12 mo
Terms used on this page
HVDC
High voltage direct current. Lower losses than AC over long distances.
Corridor
The strip of land the cable runs beneath, assembled from hundreds of private parcels.
Easement
A paid, permanent right to run cable under land the owner keeps. Agreed, not taken.
Converter station
Plant at each end converting AC to DC. Lead times run 36 to 60 months industry wide.
Firm power
Available on demand, not only when generation is running.